In a major delay to the Sixth Street Viaduct replacement project, the contractor in charge of its construction now estimates the bridge will be completed in early 2022, Curbed LA reported this week. The budget for the project, now expected to be completed in about three years, has increased $6 million to a total estimate of about $488 million.

Curbed LA cites a report by the Bureau of Engineering that was to be presented to the Board of Public Works on Friday, which states that the delays can be attributed to issues of coordination with multiple rail agencies involved, as well as unspecified challenges in the construction. 

New bridge design. (Rendering courtesy of NoTriangle Studio for Michael Maltzan Architecture)

The new delay pushes the project’s completion date another 20 months, to March 2022. The demolition of the bridge and subsequent construction has been blamed for increased traffic jams, especially for morning commuters traveling from Boyle Heights to downtown Los Angeles.

The iconic bridge, tied to Boyle Heights popular culture, was torn down due to concerns it would eventually collapse because of a chemical reaction affecting its cement pillars. Initially projected to be completed by this year, the completion date had been pushed to late 2020 before its most recent delay. 

The new Sixth Street Viaduct was designed by architect Michael Maltzan. A 12-acre park below the bridge is slated to begin construction in 2022 and will span the LA River in both the Arts District and Boyle Heights. Plans for the project include a skate park, soccer fields, gardens, and picnic areas.

Alex Medina served as a community reporter for Boyle Heights Beat from 2022 to 2024 and as an associate editor and reporter from 2024 to 2025. He was also a participant in the Boyle Heights Beat Youth Journalism Program from 2015 to 2018. He earned his degree from Hamilton College in 2022. In his free time, he enjoys reading and walking.

Leave a comment

Your email address will not be published. Required fields are marked *